My last project in China before transferring to Europe and Central Asia in 2008 was the Yichang-Badong (Yiba) expressway. This was a US$ 2.2 billion expressway through very challenging terrain, including the ‘Three Gorges National Park’.
It was massive—as evidenced by the following:
- 172 km of expressways and 35.4 km of inter-connecting roads
- 148 bridges for a total length of 70 km
- 75 tunnels for a total length of 61 km
- 3.75 million m3 of earthworks
- US$ 12.6 million/km
The answer was quite simple. The expressway was going ahead with or without the World Bank’s involvement. The Hubei government wanted the Bank to assist them in making the project an example of how to construct an expressway through an environmentally sensitive area with minimal impacts. Management fully supported this and I was tasked with helping realize this vision, although unfortunately I was not involved with the implementation.
It is important to note that the ‘Hubei Provincial Transport Department’ (HPTD) was committed to the environment from day one. They implemented the project and it was their vision that we helped articulate and realize. Both parties also were committed to building on previous experiences and innovating to minimize any negative environmental and social impacts.
In early June 2014 I had the opportunity to return to Yiba to visit the project along with over 100 colleagues from various development institutions as part of the ‘Environmental Community of Practice’. Yiba formed the background and case study to a great week of training on roads and the environment. In this post I highlight some of the environmental approaches on Yiba—many of which were unique and should form the basis for similar projects.
Route Selection
When building a new road, the key is to find the optimum alignment. During our ‘identification’ mission we travelled the entire length of the proposed alignment over several days, carefully reviewing the proposed locations of the expressway, interchanges, interconnecting roads, etc.
Some of the key considerations in selecting the final alignment were:
- Use tunnels/viaducts to reduce environmental impact
- Avoid cultural relics
- Balance materials to minimize waste deposits
- Limit cuts on slopes if at all possible to 40 meters
Waste Disposal
There was some 3.5 million m 3 of waste from excavating tunnels and other project earthworks to be disposed of. If not done correctly, this could lead to major environmental damages. Contractors—who are interested in saving money—locate waste deposit sites in the most convenient place they can, and the waste sites are often lacking proper engineering such as toe walls and drainage.
For Yiba we wanted to avoid this and so the HPTD identified 63 locations as waste disposal sitesin consultation with local authorities. The bid documents included a proper preliminary design including toe walls, drainage, slope protection and access roads. The ‘Environmental Management Plan’ (EMP) then included a clear description of the waste sites and actions to be taken.
Site Access Roads
When you are building a new road, there is seldom access for contractors to the site. So they end up constructing ‘access roads’. This is typically done by sending out a digger and just cutting away as the contractor thinks best, along an alignment that they have chosen.
The government was very concerned about this as not only was the Yiba expressway going through a national park, but the challenging terrain and isolation were such that there would be more access roads than usual. The solution was similar to that for the waste sites: the bid documents clearly identified where contractors would be permitted to build roads, or use existing roads, for access to their sites. General design was given for new roads—including drainage—and each road had specific mitigation measures included in the EMP.
Contractors and the EMP
The EMP is a critical document which contractors need to follow to minimize the negative environmental impacts of their projects. If they do not follow it, you end up with problems—many of which can be permanent.
One thing that contractors do understand are technical specifications. So for the Yiba project the specific EMP requirements were included in the contract in the form of technical specifications. The cost of implementation was also included in the Bill of Quantity to ensure they were properly funded.
Non-Compliance Penalties
One of the problems that we encounter in projects around the world is that contractors sometimes decide that in the interest of finishing the project quickly, they will ignore the environmental damages and then try to fix them as much as possible when the construction is done. This seldom works.
The solution developed with the HPTD was simple:
- If the non-compliance was minor, the contractor would be instructed to fix it. If this was done within a reasonable time period, nothing more would happen. If, however, they did not fix it within that time period, another contractor would be appointed to fix the work and the cost would be deducted from the next payment.
- For major non-compliance in addition to remedying it (if possible) there would be a fine.
During my visit I was told that the HPTD went even further, instituting a reward system. Each month 0.4% of the payments were put into an environmental fund. If the contractor did well, they would get that back, and potentially up to a 0.6% bonus for exceptional work. They also instituted formal awards for contractors who did the best. These two motivators made a huge difference to ensure environmental compliance.
Poor Environmental Supervision
World Bank projects typically have a consultant who is responsible for managing the civil works, as well as the environmental and social compliance, on behalf of the client. This model is used on large projects.
One of the challenges that we face is that these firms—usually staffed by civil engineers—too often miss environmental and social issues. For the Yiba project we adopted a different model. A separate contract was given to only undertake environmental supervision. There were three ‘regular’ supervision engineers for the civil works and electrical/mechanical investments, and then one for the environment.
The environmental supervision team undertook regular and detailed monitoring, and provided the HPDT information on the environmental performance. The HPDT even elevated their importance by requiring that any payment certificate to the contractor had to not only be approved by the regular supervision engineer, but also signed off by the environmental supervision engineer. This was a brilliant innovation which I’m sure gave the contractors a lot more respect for the environmental engineer.
Ensuring Citizen Participation
The only way that we at the Bank can fully meet our environmental and social safeguard policies is by engaging the public as much as possible. We do this during project preparation by undertaking extensive public consultations, but the focus is often on ensuring that people receive their due compensation for land, trees, or other resettlement related activities.
For the Yiba project, we also had an SMS based system that enabled people to advise the HPDT of issues related to the environment (or social).
Honored and Humbled
It was wonderful to go back and see what an amazing job the HPTD did on the project, as well as the way they (and the Bank team) built upon our ideas and also improved on them. The movie below will give you an overview of the incredible engineering achievement that is the Yiba project today.
It’s a real honor to have been involved with this project—it is the highlight of my career as a Civil Engineer. I was humbled when the HPDT gave the Bank team an award for our contributions to the Yiba project.
Video
Join the Conversation