Preventing renegotiation, fostering efficiency

This page in:
Lawyers usually say that “the best contract is the one you never have to pull out of the drawer” — a view that focuses on trust, common understanding and mutual advantages. And then they will add that public-private partnership (PPP) contracts, even with the best government–business relationship, are a bit more complex. That’s because they are based on incentive mechanisms that require not only regular monitoring, but also some degree of cooperation and a modicum of strategic management — the three components of PPP contract management.
Image
Photo: Wikimedia Commons
The ultimate success of a PPP contract depends on effective service delivery under conditions of sustained efficiency. The efficiency comes from linking private operator rewards to performance over the long-term (output focus), and from providing credible commitment by the private partner through private finance (or, as it’s known in some circles, “hostage capital”).
There are many cases, as seen in previous issues of Handshake, of PPPs providing high-quality reliable service to users at a reasonable cost for users and taxpayers. But there is also recognition that, over the long-term, PPP efficiency may be jeopardized by contract renegotiation — by necessity renegotiation under no competitive pressure, with asymmetrical information.

This sort of renegotiation creates a risk of breaking the initial commitment, changing rewards and risk allocation. Though theoretical economists would say 
that “in the long-term” renegotiation of incomplete contracts is unavoidable, PPP practitioners should do their best in order to avoid the need for renegotiation, while simultaneously preparing for renegotiation when it is the best solution in terms of public interest.
This requires distinguishing from among the several different sources of renegotiation: poor contract management, poor contract design, poor project selection, or simply the opportunistic behavior of myopic public authorities.

Why renegotiation happens
A recent OECD publication addresses several different contexts and characteristics of PPP renegotiation. This reflects a roundtable discussion connecting PPP practitioners and researchers, where the focus moved from the mere characterization and classification of renegotiation processes to the much needed recommendations on how to prevent unnecessary renegotiation.

Few renegotiations result from the dynamic inconsistency that game theory warns about — governments signing a con-tract allocating risks and rewards to the private partner, and later trying to grab part 
of the upside when projects are successful due to private sector efforts. But the fact that this kind of opportunistic behavior is rare demonstrates that PPP contracts have been successful in preventing that behavior.
There is a common realization that a large class of PPP renegotiations result from another type of opportunistic behavior, in this case shared by both parties. Here, for budgetary reasons, or due to rent-seeking, public authorities do contract PPPs for a part of what is needed, they then renegotiate the contract to enlarge its scope, in a non-competitive process that usually results in rents (extra profits) for the incumbent private operator enjoying superior information about the project and a long-term mandate for managing it.

In this case, renegotiation does not result from exogenous change, and both parties are glad to renegotiate: the public authorities in order to introduce the additions that they choose to keep out of the contract when they originally closed the deal; and the private operator because they will discuss the cost of those additions under no competitive pressure. No improvement in the contracts, or in contract management, can avoid renegotiation in this case.
The obvious solution lies in improvements in the public investment management (PIM) process (better scrutiny), in the procurement framework (less acceptance of changes to project scope, and more transparency on renegotiation), and in the fiscal framework (due consideration to medium- and long-term infrastructure and service needs, and added fiscal transparency).
Another large class of renegotiation processes results from poor contract design. In this case, contracts are more “incomplete” than what actual uncertainty would suggest. The reasons range from too much pressure for fast results (having the deal closed, even if all risks were not dully considered), or from sweeping the difficult issues under the carpet, simply transferring them from the tender phase (under competitive pressure) to the construction or operational phases (when there is no competition, and when the private operator has a maximum of bargaining power).

For these cases, the obvious solution is allowing more time for project preparation or for competitive negotiation during tender, and investing more on high-quality transaction advisors.
A component missing from many of these contracts where renegotiation is unavoidable, is a proper assessment of all the risks that the project may conceivably face. This assessment defines mitigation measures for some and prescribing courses of action for the others. Another component often missing in these cases is a good financial model that allows for risk impact to be evaluated. These are models that procuring authorities should build and use for structuring the project, and models that bidders should be required to build in order to demonstrate the ability of their proposals to satisfy the contract and face risks.
PPP efficiency may be jeopardized by contract renegotiation — renegotiation under no competitive pressure, with asymmetrical information. This sort of renegotiation creates a risk of breaking the initial commitment, changing rewards and risk allocation.

A minor but still relevant class of renegotiation processes results from poor contract management by the public partner, building an overload of disputes and miscommunication that allows the project to underperform and leads to renegotiation or contract cancelation. Many public authorities are strengthening efforts towards improving contract management practices.
Another still relevant class relates to poor private sector performance — in practice, cases 
where the private operator is able to convince the public authority that it pays to renegotiate the contract instead of canceling it. This class should be considered a sub-class of that which was previously referred to, as only poor contract management practices can allow for underperforming private operators to co-opt public authorities into a renegotiation process.
The last class of renegotiation processes, a very small one, deals with cases where there was a real significant change in the conditions for project implementation that precludes the normal execution of the contract, and so forces renegotiation because the options are contract collapse or underperformance. These cases, the ones that are truly unavoidable, will have a significant probability of happening during the life of a long-term contract, but a small probability of happening in each year of the contract.
Identifying and analyzing the myriad reasons behind renegotiation is the first step toward preventing renegotiations from taking place. Indeed, much can be done to reduce the prevalence of PPP renegotiation, which in turn will allow PPPs to demonstrate their potential efficiency. Improving the public-sector governance of PPP processes and the quality of project structuring has the potential to improve the quality of life for many people around the world.

Authors

Rui Monteiro

Senior PPP Specialist

Join the Conversation

The content of this field is kept private and will not be shown publicly
Remaining characters: 1000